Ø Attaching
a Job Plan to a work order creates task work orders for the operations
mentioned in the job plans. All these work orders inherit the location and asset
from the work order (main) to which job plan was attached. These work orders
also have the parent as the main work order.
Ø Making a
work order as parent to an existing work order does not inherit the
location and asset to the child from parent.
Ø Applying a
route to a work order creates Child Work Orders (not the task work orders)
for route stops mentioned in route definition. If a route stop has job plan
attached, there will be task work orders (Activities) created, for the
operations mentioned in job plan, attached to the child work orders created
earlier.