The Next
Due Date in a PM Schedule is the date on which you need to start executing the
PM WO. If you select the checkbox “Use Last Work Order's Start Date to
Calculate Next Due Date” the Next Due Date for a PM is calculated by MAXIMO
based on frequency and first start date, and is a read-only field. If you want
to postpone or pre-pone a certain PM task because of any reason, you can do so
by entering the new date in the extended date field. In this case, MAXIMO will
ignore the date in the Next Due Date field and will consider the value in
Extended Date field as Next Due Date. After MAXIMO creates the WO based on
Extended Date, the extended date field will become clear and next due date will
be populated based on the frequency.
Similarly if the checkbox “Use Last Work Order's Start Date to Calculate Next Due Date” is unchecked the completion date of the last PM work order is used to calculate the next due date.
Similarly if the checkbox “Use Last Work Order's Start Date to Calculate Next Due Date” is unchecked the completion date of the last PM work order is used to calculate the next due date.
Many thanks for your explanation.
ReplyDeleteMay I ask, I have all of the PM’s set to the 20th each month. How can I keep them all to generating the target start of the 20th of each month.?
ReplyDeleteAre you supposed to check the box on the frequency page? Use last start date to determine next due date? I would like to generate so the target start is always the 20th of every month…please.??