If you change the Work Order
status to INPRG, Maximo populates the Actual Start date by system
date&time. However, you can edit this date. Maximo will prevent a future
date in this field.
If you change the Work Order
status to COMP, Maximo populates the Actual Finish date by system
date&time. However, you can edit this date. Maximo will prevent a future
date in this field. This date should not be less than the Actual start date.