If you specify a task in a Plan tab of Work Order or attach a Job Plan to a Work Order, MAXIMO shall automatically create Work Orders for all the tasks mentioned in the Job Plan or task in Work Plan. These Work Orders are called Task Work orders and are exactly same as the regular work order. These Work Orders shall be the Child Work Orders for the Work Order to which you are attaching the task or Job Plan. You can further attach some more tasks/Job Plans to these child Work Orders and MAXIMO shall again create the child work orders for these tasks/Job plan; thus building an unlimited (ideally) WO hierarchy (Parent -Child relationship).