You can return a material which was issued from inventory to Work
Order. You can do so by inserting a new row in Work Order Material Actuals tab
with Transaction Type as “Return”. However, if the issue to the Work Order was
because of a direct-issue item, then you cannot use the Work Order Material
Actuals. In this case, you can return the material to vendor by using Receiving
application. Provide PO Number against which the material was received.
This blog is meant to share the understanding in asset management space. Feature differences, pros & cons with any competitor solution for maximo available in market are welcome.
Tuesday, 29 September 2015
Monday, 28 September 2015
How Maximo Avoids Creation of Duplicate Work Orders
If you create a work order on an asset/location with a failure
class & problem code and if there already exists a work order with same
combination (asset/location, failure class & problem code), maximo gives
you a warning stating that problem has already been reported. You can skip the
creation or go ahead with the creation.
This is optional, depends upon the organization settings under Work
Order Options>>Other Organization Options>>Display Duplicate Problem
Warning section.
Courtesy: An old compilation from Infy Team
Sunday, 27 September 2015
Some Tips on Applying a Job Plan / Route to a Work Order
Ø Attaching
a Job Plan to a work order creates task work orders for the operations
mentioned in the job plans. All these work orders inherit the location and asset
from the work order (main) to which job plan was attached. These work orders
also have the parent as the main work order.
Ø Making a
work order as parent to an existing work order does not inherit the
location and asset to the child from parent.
Ø Applying a
route to a work order creates Child Work Orders (not the task work orders)
for route stops mentioned in route definition. If a route stop has job plan
attached, there will be task work orders (Activities) created, for the
operations mentioned in job plan, attached to the child work orders created
earlier.
Courtesy: An old compilation from Infy Team
Saturday, 26 September 2015
Capturing Cost On Work Order
If Asset and Location both have their individual GL account defined
on them, and when you create a WO on asset, the GL Account field in Work Order
gets populated by Asset’s GL. If the asset does not have any GL Account, then
this field gets populated by location’s GL.
Courtesy: An old compilation from Infy Team
Friday, 25 September 2015
Work Order Status Flow
The Work Order Cycle has the following main statuses:
WAPPR: Work Order Waiting for Approval. WOs are created in this status (Quick Reporting WOs are created in INPRG status).
APPR: Work Order Approved. Materials are reserved at this status.
WMATL: Work Order Waiting for Materials. After approval, if there is a PO for materials required to execute the WO which has not been received yet, the WO will remain in this status.
INPRG: Work Order In progress. Indicates that WO is being executed (Actual Start Date gets auto-populated).
COMP: Work Order Completed. Indicates that WO execution is done (Actual Finish Date gets auto-populated).
CLOSE: Work Order Closed. All reviews are done and WO is electronically closed.
You can directly go from WAPPR to CLOSE, bypassing all intermediate statuses. Same logic holds good for INPRG and COMP.
Courtesy: An old compilation from Infy Team
Thursday, 24 September 2015
Working On Start Center Result Set
If you use an application very frequently and want a specific set of its records be displayed on the first screen after login, you can configure the Start Center
to get something like this.
Step 1:
Go to the application who’s data (records) you want to extract.
Make a Query to pull the specific record set and save it (need not be public).
Lets say, the application is Work Order and the where clause is the Owners =
Inventory Team
Step 2:
Go to Start Center/Change Layout and Configuration/ Right Column
Select Content = Result Set
Finished
Step 3:
Go to Start Center / Result Set – pencil icon (Edit Port
let)
Select Query created above
Select Chart Options
Show Chart by Default?
Yes
Chart Type Bar (in this case)
Display By
Status
(in this case)
Courtesy: An old compilation from Infy Team
Wednesday, 23 September 2015
Some Rules on Work Order
Ø Reservations are cancelled if a Work Order is
closed.
Ø Reorder routine does not consider the items
from a closed WO.
Ø PR generated for a WO cannot be
approved if WO (with a direct issue item) requesting that item has been closed.
Ø PO generated for a WO cannot be
approved if WO (with a direct issue item) requesting that item has been closed.
Anyhow while closing the WO, maximo will notify that an open PO exists for it,
but will let you close the WO.
Ø If you try closing a WO which has been
referenced in an open PO , Maximo gives warning
but does not force.
Ø Even if the PO
is approved, receipt is not allowed for a Closed WO.
Ø Items cannot be issued using Inventory
application to a cancelled or closed Work Order.
Courtesy: An old compilation from Infy Team
Tuesday, 22 September 2015
Working With a Work Order Record
You can delete a Work Order, if it is in WAPPR status. If you
approve a Work Order and un-approve to bring it back to WAPPR, then you cannot
delete the Work Order record.
If a Work Order has ever reached to APPR, you cannot
delete it. When you close or complete a Work Order without approving it, maximo internally treats it as approved before closing (or completing). You will
anyhow not see this in Work Order History.
Courtesy: An old compilation from Infy Team
Monday, 21 September 2015
The Resources Module in Maximo [People, Person Groups, Crafts, Labor, Qualification]
The Resources module in maximo has got following applications:
- People
- Person Groups
- Crafts
- Labor
- Qualification
Every Maximo user should have a person record associated with it in maximo. You create the users using Security Groups Application. When you create
a user, maximo automatically (optionally) creates the person for that user.
A labor record also should have a person record associated with it.
Use People application to create a Person record.
A person group consists of people who may or may not be labors.
Qualification application is used to specify the certifications,
licenses. Labor records can be linked with qualifications.
Courtesy: An old compilation from Infy Team
Sunday, 20 September 2015
Working With Priorities- Continued
If the Work Order is being created by a PM, then the PM priority
takes precedence on asset and location (i.e. gets defaulted to Work Order). If
PM does not have a priority defined, then asset priority takes precedence.
Courtesy: An old compilation from Infy Team
Saturday, 19 September 2015
Working With Priorities
If Asset and Location both have their individual priority defined,
and when you create a WO on an asset, Location gets populated. The Asset/Location
priority field in Work Order gets populated by Asset priority. If the asset
does not have any priority, then this field gets populated by location
priority.
Courtesy: An old compilation from Infy Team
Friday, 18 September 2015
Who Pays For The Work Order
If “Charge to Store” field on
Work Order is checked, the cost of the work order shall not be charged to Asset
on which the work order is written. You can see this value in the Inventory
Cost field available on the asset.
If the asset on the work order
is a non-capitalized rotating asset not located in an operating location or a
storeroom, Maximo selects the check box; otherwise this check box is cleared.
If the work order has
been written on a location (without an asset), you cannot select this check box.
Courtesy: An old compilation from Infy Team
Thursday, 17 September 2015
Interaction Node in Maximo Workflow
In MAXIMO Workflow you can design workflow
process wherein one workflow process can call another. This is facilitated
through the "Interaction Node". The second process is NOT a sub
process of the first one but an altogether individual one.
Courtesy: An old compilation from Infy Team
Wednesday, 16 September 2015
Creating Users And Custodians For an Asset
In
maximo, you can specify a user and a custodian for an asset or location. There
can be multiple custodians and users for an assets or location. You can also
make one of the user/custodian as primary. A user is normally a person who uses
the asset/location (like the persons in operations). A custodian is normally a
person who owns the asset/location (like the maintenance personnel).
Courtesy: An old compilation from Infy Team
Tuesday, 15 September 2015
Work Order Classes And How to Create These Types of Work Orders
There is a read-only field “Class” on Work Order Screen.
There are following four types of Classes:
- Work Order – Populates when you simply create a work order
- Activity – Creates when you create a task (basically a
task work order)
- Change – When you create a change to specify that some
more work needs to be done. (This is actually a follow-up work)
- Release – When you create a release. (This is also a
follow-up work)
Courtesy: An old compilation from Infy Team
Monday, 14 September 2015
Cannot Log Actuals Against a Work Order
If the Accept Charges check box
on Work Order is not checked (cleared), you cannot report any actuals against
this Work Order. You can also not plan for any direct issue material for this
Work Order.
Courtesy: An old compilation from Infy Team
Sunday, 13 September 2015
Edit-ability of Actual Start and Finish Date of a Work Order
If you change the Work Order
status to INPRG, Maximo populates the Actual Start date by system
date&time. However, you can edit this date. Maximo will prevent a future
date in this field.
If you change the Work Order
status to COMP, Maximo populates the Actual Finish date by system
date&time. However, you can edit this date. Maximo will prevent a future
date in this field. This date should not be less than the Actual start date.
Courtesy: An old compilation from Infy Team
Saturday, 12 September 2015
Task Work Orders in Maximo
The
task workorders are distinguished by normal workorders by a database field
in WORKORDER table known as "ISTASK".
If this field is set to "Y", i.e. the workorder is a task. You cannot
attach a workorder to a task workorder as its child.
Courtesy: An old compilation from Infy Team
Friday, 11 September 2015
Work Packaging
Work Package functionality
allows us to combine multiple Work orders (irrespective of their individual
statuses) by assigning them to a new parent Work Order. This parent work order
does not have any asset/location or GL and will be in WAPPR at the time of
creation.
Use Work Order Tracking
application for this. Go to list tab, search for the work orders which you want
to group, based on some common characteristic. Select all/few of them, click on
the Action Item "Create Work Package". Maximo will create a parent WO
in WAPPR without any asset/location, having all the selected WOs as children.
Courtesy: An old compilation from Infy Team
Thursday, 10 September 2015
Location Systems in maximo
SYSTEMS
in maximo is a logical grouping of locations. In order to have a location to be
a child/parent of another, both the locations should belong to a system. Use
"Associate Systems with Location" action item available in Location application
for this. Within a system, there can be only one top level location. All other
locations within that system should be children of the top level location.
One location can have more than one parent, but not in same system. One location can belong to multiple system and have multiple parent in these systems.
You can have a child location as parent of its parent, provided the system to which all of these locations belong is "Network".
Courtesy: An old compilation from Infy Team
One location can have more than one parent, but not in same system. One location can belong to multiple system and have multiple parent in these systems.
You can have a child location as parent of its parent, provided the system to which all of these locations belong is "Network".
Courtesy: An old compilation from Infy Team
Wednesday, 9 September 2015
GL Account Setup and associated tables
If a
transaction in MAXIMO involves cost (e.g. Work Order actuals), the cost need to
hit a GL account (rather two, debit and credit). In order to setup the GL
accounts, following steps need to be taken in sequence:
1. "GL account configuration" action item in "Database Configuration" application. Here you specify the number and details of segments, your chart of accounts should have. For example, you can have 1st segment as Cost Center, 2nd as Activity and so on. You can also specify the length of the segment. Here you also specify that this segment is mandatory or not during a transaction.
2. Use "GL Component Maintenance" action item in "Chart of Accounts" application to specify the values for the segments you have defined in previous step. e.g. values 100, 200, 300 etc for 1st segmentCost Center .
A5, B5, C6 etc for 2nd Segment Activity.
3. Use main tab in "Chart of Accounts" application to combine these segments to form a GL account for an organization. e.g. 100-A5 for a particular activity within a particular cost center.
Here are the underlying tables GL accounts:
GLCONFIGURE: Structure of a GL account is defined here
GLCOMPONENTS: All the possible values of individual segments are specified here [ segments are referred to as GL orders in table]
CHARTOFACCOUNTS: All the valid combinations of segments\components [valid GL account ] are listed here
1. "GL account configuration" action item in "Database Configuration" application. Here you specify the number and details of segments, your chart of accounts should have. For example, you can have 1st segment as Cost Center, 2nd as Activity and so on. You can also specify the length of the segment. Here you also specify that this segment is mandatory or not during a transaction.
2. Use "GL Component Maintenance" action item in "Chart of Accounts" application to specify the values for the segments you have defined in previous step. e.g. values 100, 200, 300 etc for 1st segment
3. Use main tab in "Chart of Accounts" application to combine these segments to form a GL account for an organization. e.g. 100-A5 for a particular activity within a particular cost center.
Here are the underlying tables GL accounts:
GLCONFIGURE: Structure of a GL account is defined here
GLCOMPONENTS: All the possible values of individual segments are specified here [ segments are referred to as GL orders in table]
CHARTOFACCOUNTS: All the valid combinations of segments\components [valid GL account ] are listed here
Courtesy: An old compilation from Infy Team
Tuesday, 8 September 2015
Closing a Work Order That is Waiting for Materials
If you
try closing a Work Order which is waiting for materials, MAXIMO shall display a
warning message. If you close the work order and try receiving the direst issue
material against the PO , MAXIMO will not allow
you to do so.
Courtesy: An old compilation from Infy Team
Monday, 7 September 2015
Reorder Process for Work Orders Waiting for Materials
If a
Work Order is waiting for materials, i.e. the status is WMATL, then you need to
run the reorder items process (can also be auto scheduled using cron task).
This process checks all the Work Orders which are in WMATL status, and then
creates the PRs for those items, keeping WO number as a reference in the PR.
The "Issue on receipt" checkbox is also checked by MAXIMO for this
process. User needs to convert those PRs into POs and then receive the material
against these POs. The PO also has the work
order reference number (copied from PR) and also "Issue on receipt"
check box checked. When you receive the material, based on "Issue on
receipt" and work order reference, MAXIMO issues the material to Work
Order.
Courtesy: An old compilation from Infy Team
Courtesy: An old compilation from Infy Team
Sunday, 6 September 2015
Direct Issue Items
If you
have mentioned a direct issue item (material) in plans tab of the Work Order,
and when you approve the Work Order, the work order status changes to WMATL
(not APPR). i.e the work order is waiting for material to arrive. Once you have
received the material, the work order status changes automatically to APPR.
NOTE: Direct Issue items are items which you want to purchase and to be directly delivered to your work location instead of passing through the storeroom.
NOTE: Direct Issue items are items which you want to purchase and to be directly delivered to your work location instead of passing through the storeroom.
Courtesy: An old compilation from Infy Team
Saturday, 5 September 2015
Movement of an Asset Between Operating Location and Storerooms
If you
want to move an asset from one operating location to another operating
location/storeroom, you can do so by using Move/Modify Assets action item
available in Asset and Work Order applications. You cannot use this action
item, if you want to move an asset from a storeroom location to an operation
location because moving out an asset from storeroom is an inventory transactions,
hence you should use issue item functionality available in Inventory Usage
application. You can also use Inventory Usage application if you want to move
an asset from one storeroom location to another storeroom location.
Courtesy: An old compilation from Infy Team
Courtesy: An old compilation from Infy Team
Friday, 4 September 2015
Calculation of the Next Due Date in a PM
The Next
Due Date in a PM Schedule is the date on which you need to start executing the
PM WO. If you select the checkbox “Use Last Work Order's Start Date to
Calculate Next Due Date” the Next Due Date for a PM is calculated by MAXIMO
based on frequency and first start date, and is a read-only field. If you want
to postpone or pre-pone a certain PM task because of any reason, you can do so
by entering the new date in the extended date field. In this case, MAXIMO will
ignore the date in the Next Due Date field and will consider the value in
Extended Date field as Next Due Date. After MAXIMO creates the WO based on
Extended Date, the extended date field will become clear and next due date will
be populated based on the frequency.
Similarly if the checkbox “Use Last Work Order's Start Date to Calculate Next Due Date” is unchecked the completion date of the last PM work order is used to calculate the next due date.
Similarly if the checkbox “Use Last Work Order's Start Date to Calculate Next Due Date” is unchecked the completion date of the last PM work order is used to calculate the next due date.
Courtesy: An old compilation from Infy Team
Thursday, 3 September 2015
How maximo creates Work plan from Job plan
If you
specify a task in a Plan tab of Work Order or attach a Job Plan to a Work
Order, MAXIMO shall automatically create Work Orders for all the tasks
mentioned in the Job Plan or task in Work Plan. These Work Orders are called
Task Work orders and are exactly same as the regular work order. These Work Orders
shall be the Child Work Orders for the Work Order to which you are attaching
the task or Job Plan. You can further attach some more tasks/Job Plans to these
child Work Orders and MAXIMO shall again create the child work orders for these
tasks/Job plan; thus building an unlimited (ideally) WO hierarchy (Parent
-Child relationship).
Courtesy: An old compilation from Infy Team
Wednesday, 2 September 2015
Asset creation and inventory update while receiving of a rotating item
If you raise a purchase order for an item which is rotating, then during receipt process of that PO, MAXIMO will ask you to enter the individual (new) asset number also so that the PO receipt process will increase the inventory and will create those many asset as well in the storeroom location; thus keeping the total count of asset equal to inventory on-hand quantity.
Courtesy: An old compilation from Infy Team
Tuesday, 1 September 2015
Continued..Difference between asset, rotating asset, sub assembly and spare part
As you
make an item as rotating and then attach that item to an asset; thus making asset
rotating.
If you want to adjust the current balance of an item (spare parts), you can do so by using the Action Item "Inventory Adjustment>> Current Balance". If you try using this Action Item for a rotating item, MAXIMO would not allow you to do so, because if an item is rotating, then you may also have the asset attached to it; thus making asset count not matching with the current balance of the item.
Whenever, you add or delete a rotating asset, MAXIMO automatically increases or decreases the current balance of that item (attached to asset).
If you want to adjust the current balance of an item (spare parts), you can do so by using the Action Item "Inventory Adjustment>> Current Balance". If you try using this Action Item for a rotating item, MAXIMO would not allow you to do so, because if an item is rotating, then you may also have the asset attached to it; thus making asset count not matching with the current balance of the item.
Whenever, you add or delete a rotating asset, MAXIMO automatically increases or decreases the current balance of that item (attached to asset).