The Required Date for an item in Work Plan Materials tab is
populated by Schedule Start Date for the 1st time. It works in
following way for different kind of items:
1. Stock
Items – Required Date is read-only and gets populated by Schedule Start Date
for the 1st time. Further changes to Schedule Start date do not get
a reflection in Required Date. However, during material reservation on WO
approval, the materials get reserved as per the Schedule Start Date bypassing
the required date.
2. Direct
Items – Required Date is editable and gets populated by Schedule Start Date for
the 1st time. Further changes to Schedule Start date do not get a
reflection in Required Date. You can manually edit this date and PRs get
generated based on this date (Required Date).
In both the above cases, if
Schedule Start Date has not been specified, then Target Start Date gets
defaulted to Required Date. If both the dates are present, then Schedule Date
takes precedence over Target Date. If none of the date exists, then system date
is defaulted.