If you create a Work Order
from a PM, which has a Job Plan attached to it, Maximo copies the Job Plan’s
Duration to Work Order’s duration and also populates the Target Finish Date as
target Start Date + Duration. However, manual creation of Work Order does not
follow this rule.
Courtesy: An old compilation from Infy Team